Water
EVALUATION, DESIGN, AND CONSTRUCTION
WATER SYSTEM REHABILITATION
ROUNDUP, MT

Planning
- 2009 CIP
- 2009 PER
- 2010 Grant Applications
- 2010 CIP Update
- 2011 PER Update
- 2012 CIP Update
- 2012 Grant Applications
- 2013 PER Update
- 2014 CIP Update
- 2014 Grant Applications

Phase 1
- 6,000 LF Water Main
- Well Pump and Well House Upgrades
- By-Pass Existing Infiltration Gallery
- New Service Lines to Curb Stops
- Completed In 2013

Phase 2
- 5,600 LF Water Main
- Abandonment of 5 Blocks of Old Main
- New Water Meters
- New Service Lines to Curb Stops
- 2 Block of Full Street Restoration
- Completed in 2015

Phase 3
- 7,200 LF Of New Water Main
- Increase Fire Flow to New School
- Transmission Main Replacement